How many people in Swampscott have passed the end of Archer Street without knowing there was a woods behind it? Holden Hersey is the Eagle Scout who built the trail's signs and kiosk, and he told Itemlive he was in the same position. "Before the project, I didn't know this area existed, but I checked it out." He said it was small enough to walk around, yet "somehow I got lost. So I was like, 'I think I need some signs here.'"
That woods has been officially open since the town held the ribbon-cutting on Friday, October 9. The trail runs about three-quarters of a mile and has four entrances. Only one of those entrances has anywhere to park, and that was planned. Almost every choice made about this land, from the 2022 purchase to the width of the path, points the same way. Archer Woodlands is a woods for people who walk in from the streets around it.
The place goes by several names. The Swampscott Tides calls it the Archer Trail. The Town's October newsletter and Hersey's kiosk call it Archer Woodlands. Itemlive covered the opening as Archer Street Park. All three mean the same woods.
The Front Door Is at the End of a Side Street
The main entrance is at the end of Archer Street. Hersey's kiosk stands there, built from lumber and materials that Home Depot donated. Swampscott Conservancy President Toni Bandrowicz said the kiosk will eventually carry flyers and information about the trail. Until then, the signs at the entrances are how you find your way.
The Town's October 2026 newsletter explains how to get in.
Entrance | Parking | Notes |
|---|---|---|
End of Archer Street | Limited | Main entrance, Hersey's kiosk |
End of Vaughan Place | None | Walk-in access, trail sign |
End of Connelly Avenue | None | Walk-in access, trail sign |
Park Street | None | Walk-in access; the Town newsletter calls this access point Park Square |
Hersey put up signs at three entrances and built the kiosk at the fourth.
The town never intended to add parking. At a public meeting in January, DPW Director Gino Cresta said that because every entrance sits in a residential neighborhood, there were no plans for parking lots or extra on-street spaces, and that he did not "envision a lot of cars coming to park around these trails," according to the Swampscott Tides. If you live within walking distance of Vaughan Place, Connelly Avenue or Park Street, the trail starts a short walk from home. Everyone else should plan on finding one of the few spaces on Archer Street, or parking somewhere legal farther away and walking the rest.
Two Trails Inside One Small Woods
Once you're in, there are two different experiences. Itemlive's coverage of the opening describes two trail systems. One is a walking path surfaced in stone dust, with boardwalks over spots that get wet in certain seasons. The other is a more rugged hiking trail through the woods. Itemlive's photo coverage also shows the view from a lookout on the property.
The rough sections surprised at least one person who pushed for the project. Tania Lillak, who chairs the Open Space and Recreation Committee, told the Swampscott Tides at the ribbon-cutting:
"I didn't realize it was as rugged as it was. I think a lot of people wanted that, and I think there was a lot of push for gravel. It definitely feels like you're in nature."
At the January meeting, the builders described a plan that adds little to the land. Justin Savickis, landscape project manager for Greener Group, said several large boulders on the route would be used as resting spots instead of benches, and that vegetation cut during clearing would stay on site, spread through the woods. The Tides describes the finished trail as winding through a quiet wooded area, away from nearby traffic, with birdsong along the path. Its July coverage called the path clean and well maintained, suited to an easy walk or birdwatching.
Hersey, a member of Troop 53, also cleaned up the woods as part of his project. Scoutmaster David LaPorte told the Tides that they picked up "half a century's worth of glass" inside the property.
Why the Path Is Three Feet Wide
The narrow path traces back to a dispute that stopped construction this spring, four years after the land was bought.
- June 2022. A Special Town Meeting approved buying several properties, including the Archer Street parcel and the former Hawthorne-by-the-Sea site. The Archer Street land had previously been slated for a large housing redevelopment.
- 2024. The town applied for a state grant. Town Meeting set aside $225,000 for construction and accepted a $112,500 state grant.
- February 2025 onward. STV Inc. led design and engineering, with public meetings in February 2025. Greener Group later won the construction contract, which the Tides reported in January 2026 as awarded in October.
- April 15, 2026. Town Administrator Nick Connors told the Select Board that work was on hold until the Conservation Commission could review it. Neighbors had raised flooding concerns and said the construction differed from the plan they had been shown, the Swampscott Tides reported. Connors walked the site with them.
- Late April 2026. The Conservation Commission voted unanimously to let the trail go ahead near wetlands on two conditions: a short spur would be removed, and the trail would be narrowed to three feet, the Tides reported.
- July 2026. The Open Space and Recreation Plan Committee reported that the paths and bridges were ready for visitors and that nearly all the signs were up.
- October 9, 2026. Ribbon-cutting at the Archer Street entrance.
The emails from neighbors that the Tides reviewed all raised flooding concerns, and they also said they appreciated "the town's efforts to preserve this land." Community and Economic Development Director Marzie Galazka said at the commission meeting that the intention was "not to cause harm" to the neighborhood or the wetlands.
The three-foot figure has a regulatory background. In its coverage of the vote, the Tides noted that Galazka said the project was originally considered exempt under state regulations, and that under the Wetlands Protection Act regulations it cited, unpaved pedestrian walkways narrower than three feet that provide public access on conservation property are among the minor activities exempt from permitting. For a walker, the practical effect is a narrow path where groups go single file.
The January plans also mentioned a loop around the radio tower on the property and said the town was still deciding whether the tower might eventually come down. The opening coverage did not say whether that loop was built, so expect to find out when you walk it.
Where Archer Fits Among Swampscott's Inland Walks
At the opening, Bandrowicz called the parcel "a small patch of open space" in a town "where open space is a rarity," according to Itemlive. Open Space and Recreation Committee member Shauna Vera, who lives nearby, told the Tides, "It's great to not have to figure out where we need to go."
Archer adds to a short list of inland spots that the Swampscott Conservancy features as Special Places. Like Archer, most are entered from a neighborhood street or a school or church lot:
- Charles M. Ewing Woods. A 7.3-acre conservation parcel beside the Stanley School on Whitman Road. You can enter from the end of the Forest Avenue extension, or from the Unitarian Universalist Church of Greater Lynn lot or the Stanley School lot when school is out.
- Forest River Conservation Area Connector. Behind Swampscott Cemetery on Essex Street, down the steps from the dog park, which has limited parking. It connects to the 2.5-mile trail network of Salem's Forest River Conservation Area, which covers more than 97 acres and includes Eagle Hill.
- Jackson Park Woods. A large unimproved area behind the high school.
- Muskrat Pond. A small freshwater pond next to Forest Avenue near the Middle School, reached from Forest Avenue or the Middle School parking lot exit.
The Rail Trail will eventually link more of the town, though not soon. The open segment runs from Bradlee Avenue to the Marblehead town line, according to the Friends of the Swampscott Rail Trail. In March 2026 the regional MPO pushed completion of the rest to fiscal year 2029, the Swampscott Tides reported. Hersey told Itemlive he first considered doing his Eagle project on the Rail Trail before the town asked him to look at the Archer woods.
For now, Archer Woodlands is the newest walk in town. It's about three-quarters of a mile of stone dust, boardwalk and rough trail, and it starts at the end of Archer Street.
If walking Archer has you curious about which Swampscott streets are a short walk from these pocket woods, or what the 2022 open-space purchases mean for the neighborhoods around them, Andrew knows this part of town street by street. Get a Free North Shore Market Consultation, and we can talk it over, on the trail if you like.